Address:
4545 Jimmy Doolittle, Suite 200
Addison, TX 75001
Management Office Hours:
Monday - Friday
8am - 5pm
Airport Front Desk: 972-392-4850
After Hours Maintenance: 214-683-1351
Operations: 972-392-4861
3/31/2022:
Addison Airport has an upcoming airport project that includes surface treatments on the runway and Taxiway Alpha. The work will require Runway 16-34 and Taxiway Alpha to be closed for 4 or 5 days for all aircraft operations, followed by an additional weekend closure to apply the final pavement marking . This project will include Runway Taxiway Alpha and the connecting taxiways (east of the runway), rubber removal, paint removal, cleaning and sealing cracks, surface treatment of the runway and the parallel taxiway system (TWY A and East Connectors).
The project will begin on Friday, April 8, at 8:00 pm. with a 4- or 5-day closure. We will be providing updates on this page during the project.
Also, please note we have had a runway designation change, from 15-33 to 16-34. FMI: joe.mcanally@addisonairport.net
2/09/2022:
Addison Airport has rescheduled an airport project that includes surface treatments on the runway and Taxiway Alpha. This project is important to preserve the integrity of the runway. The work will require Runway 15/33 and Taxiway Alpha to be closed for 4 or 5 days for all aircraft operations, followed by an additional weekend closure to apply the final pavement marking . This project will include Runway 15/33 and Taxiway Alpha and the Connecting taxiways (east of the runway), rubber removal, paint removal, cleaning and sealing cracks, surface treatment of the runway and the parallel taxiway system (TWY A and East Connectors).
The project is now scheduled for a start date of Friday, April 8, with a 4- or 5-day closure beginning (most likely) at 8:00pm on April 8. We will provide you with additional detail and a specific schedule as we get closer to the schedule.
Additionally, the project will include a change of the runway designation, from 15-33 to 16-34.
We will provide you with additional details, dates and times when the engineers finalize the schedule.
11/24/2021:
After discussions with TX-DOT Aviation and the airport engineers, the runway/taxiway pavement preservation and runway re-designation project has been delayed until spring. You will receive additional information regarding the project scheduling in a few months. There will be no airport closure in December. FMI: Joe.McAnally@addisonairport.net
11/19/2021:
On Tuesday 11/16, airport staff met with the project engineer, the contractor, and TX-DOT to discuss plans and timing for the runway and taxiway pavement preservation work. The target date for a shut-down to do this work is still December 2-6, pending weather. We have set two dates on which “go/no-go” decisions must be made, with those decisions being driven by the weather. The first decision date is Wednesday 11/24. If the weather appears favorable for the 12/2 to 12/6 time frame, the contractor will order materials on that date. If the weather forecast is not favorable, we will make a “no-go” decision and postpone the project until spring. Similarly on Monday 11/29, the team will assemble to look at the weather forecast and make a decision on whether to proceed. The crack seal and seal coat products require a temperature of 55 degrees and rising to apply and cure, so if precipitation or low overnight temperatures (in the 40s) are forecast for the 12/2 to 12/6 time frame, we will postpone the project until spring.
We will advise our tenants of the “go/no-go” decision(s) on both those dates. Obviously, if the “no-go” decision is made on 11/24, there will not be a need to make any decision on 11/29 (as the decision to postpone until spring will already have been made). If you have questions, please contact joe.mcanally@addisonairport.net
11/05/2021:
After a discussions with TX-DOT Aviation and the airport engineers, the plan for the runway/taxiway pavement preservation and runway re-designation project is as follows: