Keller Springs Reconstruction
Proposition A of the 2019 Bond Program is the reconstruction of Keller Springs Road from the Dallas North Tollway to Addison Road. Keller Springs was originally built in the late 1970s with asphalt and will be reconstructed with concrete. The utilities will be upsized to handle continued growth in Addison, the Master Transportation elements will be installed, and the traffic lights at the Quorum Drive intersection will be replaced.
Status Updates
July 27, 2021
The design is 95% complete. The Town is preparing preliminary right-of-way documents and appraisals for acquisition.
March 9, 2021
The design is 65% complete. Bidding for construction is scheduled for the late summer of 2021.
August 31, 2020
The 30% conceptual design is complete. The 65% design is estimated to be completed in March of 2021.
December 10, 2019
Council has approved the design contract to Jacobs Engineering.